Parkland Ranches Roadway Enhancements

Project Overview

Parkland RanchesThe City of Parkland has hired Bergeron Land Development (BLD) to improve the drainage and resurface the roadways in the Ranches neighborhood of Parkland.

BLD will dredge the roadside canals to remove sediment to improve water flow and reduce the risk of flooding. We will also clear and grub the canal banks of vegetation to improve drainage and prevent obstruction.  Damaged or outdated culverts will be replaced to enhance stormwater management. The canal banks will be restored with Earthwork and sod to prevent erosion and provide long-term durability. The current stormwater system will be upgraded with a new outfall structure and two stormwater pumps to improve the neighborhood’s flood control.

The existing road surfaces will be milled and resurfaced, which may also include reworking the existing road base. BLD will adjust the roadway cross slopes to enhance drainage and improve safety. Where needed, driveways will be partially reconstructed to harmonize with the new road surfaces, new guardrails will be installed, along with new signage and pavement markings.

BLD will convert a portion of Trotters Lane / NW 72 Street to a one-way road, and blue raised pavement markers (RPMs) will be installed to mark fire hydrant locations.

Work began in January and is expected to take a year and half to complete.

Project Updates

The week of Monday, November 17, 2025, Bergeron Land Development will be:

  • Grading and dredging the canal on Trotters Lane. Expect lane closures and please obey flaggers directing traffic.
  • Grading and dredging the canal on Riverside Drive and 81st Street.
  • Drainage crews will be performing the drainage work on 87th at Trotters Lane and 68th Court.
  • Road crews will be regarding the existing base on 82ns Terrace and 81st Terrace.
  • Trucks will be hauling materials throughout the neighborhood.

As of November 14, 2025, BLD has:

  • Dredged and graded banks on Trotters Lane and 87th Avenue.
  • Drainage crews have completed roadway crossings on 66th Lane and started the crossing at Trotters Lane and 87th Avenue.

Questions or Comments

Thank you for visiting our website. Please check back each week for project updates.